G.O. Bond Road: Montreal Loop

Project Manager: Gillie Lopez
Office Phone: (505) 891-5049
E-Mail: glopez@rrnm.gov
Contract Company: TLC Plumbing and Utility
Cost: $  617,848.52
Stage: Construction
Schedule: June 2018 - September 2018
Montreal Loop  GO 2018
The reconstruction of Montreal Loop from Enchanted Hills Boulevard to Enchanted Hills Boulevard includes replacement of non-compliant American with Disabilities Act (ADA) curb ramps as well as improvements to roadway pavement. Areas identified as having poor subgrade will require the excavation of unsuitable material, replacement with suitable borrow, and subgrade preparation. The Contractor will replace broken curb and gutter (as identified in the plans), striping, and add collars for all utilities shown.

Additional Information:


Status Log:

  • July 2018: The road way work will start on 7/16/18 with a new traffic control setup. Montreal Loop paving will be completed in two phase and will limit access to residents only during the roadway work.
  • June 2018: Traffic Control switch to occur on June 20, 2018.
  • May 2018: Presented to Governing Body for Advice and Consent.