Unser Phase 1 Rehabilitation

Project Manager: Bill Ladd
Office Phone: (505) 891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt Inc.
Cost: $ 1,563,249.47
Stage: Construction
Schedule: August 2020 - November 2020
Unser Phase I
Phase 1 includes the rehabilitation of Unser Boulevard from Abrazo Road to Southern Boulevard. Construction will consist of mill and inlay, crack patching and crack sealing the existing asphalt surface, removing and replacing ADA ramps for compliance at intersecting streets, removing and replacing concrete sidewalk, permanent striping, and traffic control.

Road work begins August 31, 2020 and continues through November 2020. Construction will be from 7:00 a.m. to 5:00 p.m., Monday-Friday, and weekends and evening hours as needed. Business and residential entrances will be open at all times.
  • Americans with Disabilities Act (ADA) Ramps and Sidewalk reconstruction will begin in September 2020.
  • Asphalt Patching and Crack Repair will begin in September 2020.
  • Roadway Asphalt Mill and Inlay will take place during October 2020.
  • Permanent Striping of the roadway will take place during November 2020.
This project is funded via 2020 G.O. Bond dollars. Thank you, Rio Rancho voters!

NOTICE:


On November 1, 2020 the intersection of Southern Boulevard and Unser Boulevard will be closed for reconstruction between 4:00 am to 12:00 pm.  Please see the detours below.

Status Log:

August 2020:
  • Construction to begin August 31, 2020.
Adobe Disclaimer: Reading the PDF documents provided on this site requires the Adobe Acrobat Reader, available for free from Adobe. Adobe, the Adobe logo, Acrobat, and the Acrobat logo are trademarks of Adobe Systems Incorporated.