Unser Phase 1 Rehabilitation

Project Manager: Bill Ladd
Office Phone: (505) 891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt Inc.
Cost: $ 1,563,249.47
Stage: Complete
Schedule: August 2020 - November 2020
Unser Phase I
Phase 1 includeded the rehabilitation of Unser Boulevard from Abrazo Road to Southern Boulevard. Construction consisted of mill and inlay, crack patching and crack sealing the existing asphalt surface, removing and replacing ADA ramps for compliance at intersecting streets, removing and replacing concrete sidewalk, permanent striping, and traffic control.

Status Log:

August 2020:
  • Construction to begin August 31, 2020.