Southern Boulevard Phase II Final Design

Quick Facts

Project Manager: Arnell Friedt
Office Phone: (505) 896-8242
E-Mail: afriedt@rrnm.gov
Contract Company: HDR Engineering, Inc.
Cost: $ 2,391,260.60
Stage:  Design 
Schedule: April 2022 - May 2023
Southern Blvd

Southern Boulevard Phase II Final Design included Southern Boulevard from Golf Course Road to Unser Boulevard and is a similar design to the recently completed Southern Boulevard Phase I project from NM 528 to Golf Course Road. The design is funded with City funds (approximately $600,000) and Federal funds (approximately $1.8 million).

This design addresses improvements including: a widened road design for reconstruction of a four-lane divided roadway with bicycle lanes, a multi-use trial and sidewalk, right-of-way mapping, traffic signals, lighting, drainage, and utilities. 

Construction dates have not yet been determined and are dependent on funding.

Public Meeting

A virtual public meeting to discuss the final design stage was held on Thursday, May 19th from 6:00 p.m. to 6:45 p.m. To access a recorded version of this meeting, email angarcia@rrnm.gov. To download a copy of the presentation, click here.


Additional Information:

Status Log:

  • April 2023: Finalizing design
  • March 2023: Final right of way maps approved
  • February 2023: Second draft right of way maps
  • January 2023: Developing additional Environmental documents
  • November 2022: Coordination with NMDOT
  • October 2022: Proceeding to final plans for Phase IIA.
  • September 2022: Right of Way maps in review. 
  • August 2022: Right of Way maps in development. 
  • May 2022: Second Public Meeting held. 
  • April 2022: Design documents completed to 90%.
  • March 2022: Pothole drilling to locate utilities complete.
  • December 2021: Pothole drilling to locate utilities in roadway. During this time, one lane of Southern Blvd. may closed for a short period of time. 
  • August 2021: Design documents completed to 60%.
  • June 2021:

    City Project Manger and Design Consultant walked corridor and made initial contact with business owners.  Preliminary Drainage Report complete.

  • May 2021:

    Geotechnical Engineering Services and report complete.

  • January 2021:

    Topographical survey and aerial mapping complete. Subsurface Utility Engineering (SUE) Level B complete.

  • October 2020:

    Programmatic Categorical Exclusion (PCE) was issued by the New Mexico Department of Transportation (NMDOT) certifying the project does not have significant environmental impacts.

Adobe Disclaimer: Reading the PDF documents provided on this site requires the Adobe Acrobat Reader, available for free from Adobe. Adobe, the Adobe logo, Acrobat, and the Acrobat logo are trademarks of Adobe Systems Incorporated.