Northern Boulevard Reconstruction and Expansion

Project Manager: Arnell Friedt
Office Phone: (505) 896-8242
E-Mail: afriedt@rrnm.gov
Contract Company: Huitt-Zollars 
Cost: $ 1,525,369.75
Stage: Preliminary Design
Schedule: June 2021 - May 2023
Northern Blvd

This project includes the reconstruction and expansion of Northern Blvd. from Acal Place to Broadmoor Blvd. including curb and gutter, sidewalk and multi-use path, lighting, storm sewer, sanitary sewer, asphalt pavement, landscaping and pavement marking. Funding for this project is from City funds (approximately $192,000) and federal funds (approximately $1,128,000).

Additional Information:

Status Log:

  • February 2023: 90% review meeting
  • November 2022: First draft of right of way maps
  • October 2022: 90% design under review
  • September 2022: Second public meeting
  • August 2022: Begin right of way maps
  • June 2022: Working toward 90% design
  • May 2022: First public meeting
  • April 2022: Working on Environmental Studies and Public Involvement
  • March 2022: Working towards 60% design
  • December 2021: Working on 30% design
  • July 2021: Initial surveys are ongoing