Sabana Grande A.D.A. Ramp Remediation Project

Project Manager: Jarod Thiele
Office Phone: (505) 896-8805
E-Mail: jthiele@rrnm.gov
Contract Company: Altor Construction
Cost: $212,079.77
Stage: Construction
Schedule: March 2022 - April 2022
SG 16

This project involves the removal and replacement of 38 non-compliant ADA pedestrian ramps. In addition 2 driveway aprons at the MVD located at 4114 Sabana Grande Ave SE will be replaced, access will be available at all times to this property. Project limits are from NM 528 to Dolores Hidalgo Drive SE and Benjamin Drive SE.

Traffic control notifications will be delivered to affected residents and businesses. Project information will be provided on the City's website and social media. There will be minimal interruption to traffic during this project.

Funding for this project is from Community Development Block Grant, Housing and Urban Development Block Grant Funds.

map