Sports Complex North Phase 2 Construction

Project Manager: John Finley / Dyane Sonier
Office Phone: 505-896-8359 / 505-896-8728
E-Mail: jfinley@rrnm.gov / dsonier@rrnm.gov
Contract Company: T.A. Cole & Sons General Contractors, Inc. 
Cost: $2,367,200.77
Stage: Construction
Schedule: April 2022 -  December 2022
Sports Complex North Ph2 construction

The Sports Complex North Phase 2 Construction project will include demolition of existing fencing, site clearing and grubbing. New construction shall include a restroom/concession building, steel shade structure, earthwork and grading, site utilities, drainage structures, asphalt, concrete paving, concrete retaining walls and stairs, miscellaneous steel fabrications, fencing, irrigation, plantings, native seeding, site electrical and site lighting.