This project is for full roadway reconstruction between Golf Course Road and N.M. 528 with pond, ADA curb ramps, utility adjustments, and pedestrian push button improvements.
Project Work Sequence:
Sequence 1 - January to February 2023: concrete work.
Sequence 2: January to March 2023: pond reclamation.
Sequence 3: February to May 2023: roadway rehabilitation.
*At times while project work is taking place, one-way traffic with posted detours will be in place.